Overview
The Reports > Management > Project Hours Report shows the percentage of hours that have been worked against each project code, as well as the percentage that this equates to across the total workforce.
The report will only appear in portals where the Project Management module has been enabled.
On-screen Columns
The on-screen view of the Project Hours Report includes the following data:
- Projects
- Activities
- Cost Code
- Employees
- Timesheets
- Hours
- % of Worked on Project
- % of Total Workforce
Export Options
You can export the on-screen view of the Project Hours Report in .csv format.
Comments
0 comments